Abilita Sosiaalihuolto/Socialvård / Abilita Oy Ab
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Stage 1, Joining system: File attachment functionality | 13.6.2019 | 1. Completed, 27.8.2019 2. Ongoing, 12.5.2020 3. Not tested |
|
Second-stage functionalities | 8.12.2020 | 1. Not started 2. Not started 3. Not started |
|
Accepted joint testings: |
|||
Stage 1: Joining system | 30012018 / 17.4.2018 |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
Domacare / Invian Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 30.4.2020 | 1. Not started 2. Not started 3. Not started |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
Effica/Lifecare Sosiaalihuolto / Tieto Evry Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 21.12.2020 | 1. Not started 2. Not started 3. Not started |
|
Accepted joint testings: |
|||
Stage 1: Recording system | 30022018 / 18.5.2018 | ||
Stage 1: Archiving of old data | 30022019 / 9.5.2019 |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
eRA / Atostek Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 30.4.2020 | 1. Completed, 3.6.2020 2. Completed, 27.10.2020 3. Not started |
|
Accepted joint testings: |
|||
Stage 1: Joining system | 30042018 / 29.10.2018 |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
Epic / Epic Helsinki Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Stage 1: viewing system | 1. Ongoing, 6.5.2019 2. Not tested 3. Not tested |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
Saga sosiaalitoiminnot (Sosiatri) / Mediconsult Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 29.4.2020 | 1. Not started 2. Not started 3. Not started |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
SofiaCRM / Netproce Oy
Registration, return date of pre-test cases | Testing stages start date | Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 30.4.2020 | 1. Completed, 5.6.2020 2. Ongoing, 5.1.2021 3. Not started |
|
Accepted joint testings: |
|||
Stage 1: Joining system | 30032018 / 16.8.2018 |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
Vasara / Apotti Oy
Registration, return date of pre-test cases | Testing stages start date | Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
No ongoing joint testings | |||
Accepted joint testings: |
|||
Stage 1: application or service providing the data | 30012019 / 21.1.2019 |
Walmu/ Pasismo Oy
Registration, return date of pre-test cases | Testing stages start date |
Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
Second-stage functionalities | 31.12.2020 | 1. Not started 2. Not started 3. Not started |
1 = Testing between system supplier and Kela, 2 = Testing between client test organisation and Kela, 3 = Cross-testing.
X-Migrator / Visma Consulting Oy (former Avaintec Oy)
Registration, return date of pre-test cases | Testing stages start date | Statement number and date | |
---|---|---|---|
Ongoing joint testings: |
|||
No ongoing joint testings | |||
Accepted joint testings: |
|||
Stage 1: application or service providing the data | 30052018 / 3.12.2018 |